MRT Corp Still Reviewing Cost Cutting Measures For MRT2

143 views · Published 11 July 2018 · 1:23 · Indexed 29 October 2026

Channel: 7Edition · 2018 · News & Politics

Watch on YouTube

Mass Rapid Transit Corporation Sdn Bhd (MRT Corp), said it is still studying ways to reduce the cost the RM32 billion Sungai Buloh-Serdang-Putrajaya, MRT line two. 

Its project director, Datuk Amiruddin Ma'aris said analysis on ways to save costs is being done but has yet to be finalised. 

He said this is to ensure that cost cutting measures do not affect the safety and functionality of the project. 

For MRT2, a total of 48 packages has been awarded to contractors worth RM30 billion while another 20 packages worth RM2 billion is on-going.

As of early July, the construction of the MRT line two reached 30 percent completion.

With the current pace of progress, Datuk Amiruddin said the project would be able to move to the next phase of construction as scheduled.